Timeline

Project Timeline


Public Outreach & Landowner Engagement2021-2028 Conduct initial stakeholder and public engagementDevelop alternative routesIdentify preferred route Perform ongoing public outreach and engagementConstruction & Restoration 2025-2028 Perform pre-construction activities (e.g., survey, geotechnical investigations, right-of-way preparation, environmental protections installations)Build converter stations and transmission lineStabilize and restore the construction areasFeasibility & Routing Studies 2020-2022 Identify energy resources and delivery needsConduct feasibility studiesIdentify routing study area Application & Approval2023-2025 Apply for federal, state and local government permitsAcquire land agreements and right-of-way easementsProject Completion2028 Place substations and transmission line in service